US Judge to Consider Orsted Request to Block Trump Offshore Wind Halt
A U.S. judge on Monday will consider a request from Danish energy company Orsted to block the Trump administration's halt on its Sunrise Wind project off the coast of New York.The preliminary injunction request is the fifth brought by an offshore wind developer since the Interior Department's December 22 pause on five offshore wind leases in federal waters. The agency stopped work on the multi-billion-dollar facilities due to national security concerns around radar interference.Orsted has spent or committed more than $7 billion to date to build Sunrise Wind, the company said in a court filing.
Coastal Virginia Offshore Project Costs Increases to $11.5b
Dominion Energy said on Friday the total project costs for the Coastal Virginia Offshore Wind have increased to roughly $11.5 billion from $11.2 billion.The changes in estimated costs reflect the impact of temporary suspension of work issued by the U.S. government in December as well costs associated with tariffs.Earlier this month, a federal judge allowed Dominion to resume work at the Virginia offshore wind project, after it was initially suspended by the Trump administration over what it called national security concerns.The project was originally slated to be completed by the end of 2026…
U.S. District Court Allows Coastal Virginia Offshore Wind to Resume Work
Today the U.S. District Court for the Eastern District of Virginia granted Dominion Energy’s request for a preliminary injunction allowing construction to resume on the Coastal Virginia Offshore Wind (CVOW) project while Dominion Energy’s lawsuit challenging the agency’s action proceeds. Our team will now focus on safely restarting work to ensure CVOW begins delivery of critical energy in just weeks. While our legal challenge proceeds, we will continue seeking a durable resolution…
Empire Wind Granted Preliminary Injunction, Construction to Resume
The underlying lawsuit challenging the U.S. Department of the Interior’s December 22, 2025 suspension order will continue to proceed.Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period. In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.Empire Wind is being developed under contract with the New York State Energy Research and Development Authority (NYSERDA) to deliver a critical new…
US Judge Rules Orsted Can Resume Work on Offshore Project
A federal judge on Monday cleared Danish offshore wind developer Orsted to resume work on its nearly finished Revolution Wind project, which U.S. President Donald Trump's administration halted along with four other projects last month.The ruling by U.S. District Judge Royce Lamberth is a legal setback for Trump, who has spent the last year seeking to block expansion of offshore wind in federal waters. It was the second time in four months the $5 billion Revolution Wind project has sought…
US Judge Considers Orsted's Request Against Trump Offshore Wind Pause
A U.S. judge on Monday will consider a request from Danish energy company Orsted for an injunction against the Trump administration's decision to halt its $5 billion Revolution Wind project off the coast of Rhode Island.The company's lawsuit is one of several filed by offshore wind companies and states seeking to reverse the Interior Department's December 22 suspension of five offshore wind leases over what it said were national security concerns.Offshore wind developers have faced repeated disruptions to multi-billion dollar projects under U.S.
Empire to File Injunction Against Lease Suspension Order
Empire Offshore Wind LLC (Empire) filed a civil suit in the U.S. District Court for the District of Columbia today, January 2, 2026, challenging the U.S. Department of the Interior’s order directing a suspension to the Empire Wind project. As part of that case, Empire plans to seek a preliminary injunction and allow construction to continue while the litigation proceeds. While Empire continues to work closely with Bureau of Ocean Energy Management (BOEM) and the other relevant authorities to find a prompt resolution to the matter…
Dominion Energy Responds to US Suspension of Coastal Virginia Offshore Wind
Dominion Energy released the following statement in response to the U.S. Department of Interior’s Director’s Order for a 90-day suspension of work issued earlier today for the Coastal Virginia Offshore Wind project:"The Coastal Virginia Offshore Wind Project (CVOW) is essential for American national security and meeting Virginia’s dramatically growing energy needs, the fastest growth in America. This growth is driven by the need to provide reliable power to many of America’s most important war fighting installations…
Trump Freezes Five Offshore Wind Projects, Company Shares Plummet
The Trump administration suspended leases on Monday for five large offshore wind projects that are under construction off the U.S. East Coast over what it called national security concerns, sending shares of offshore wind companies plunging.The suspension was the latest blow for offshore wind developers that have faced repeated disruptions to their multi-billion-dollar projects under U.S. President Donald Trump, who has said he finds wind turbines ugly, costly and inefficient. State officials, offshore wind companies, and industry trade groups slammed the move as unjustified.The U.S.
US Government Takes Another Look at Virginia Offshore Wind Project
The Trump administration is reviewing whether to send the Interior Department's Biden-era approval of a Virginia offshore wind project back to the agency for reconsideration, according to a court document filed on Wednesday.The agency is conducting a review of offshore wind leases to comply with Interior Secretary Doug Burgum's July order to end preferential treatment for wind and solar projects, it said in a filing in U.S.
US Federal Judge Grants Go Ahead for Orsted Offshore Wind Project
Danish offshore wind developer Orsted can restart work on the nearly finished Revolution Wind project off the coast of Rhode Island, a federal judge ruled on Monday, after President Donald Trump's administration halted the project last month.The ruling is a legal setback for Trump, who has sought to block expansion of offshore wind in U.S. waters. It is a palpable victory for Orsted, which has been losing $2 million a day since the project was halted on August 22.Revolution Wind is located 15 miles off the coast.
Trump Administration to Cancel Approval of Maryland Offshore Wind Project
The administration of U.S. President Donald Trump intends to withdraw federal approval for US Wind’s offshore wind farm off the coast of Maryland, according to a filing submitted by Attorney General Pam Bondi in the U.S. District Court in Delaware on Friday.US Wind is owned by funds managed by Apollo Global Management, an American investment firm, and Renexia SpA, a subsidiary of Italy's Toto Holding SpA. The project is scheduled to begin construction next year.(Reuters)
Trump's Halt of Rhode Island Wind Project Stuns Local Leaders
The Trump administration's order to halt work on a nearly completed wind farm off the coast of Rhode Island threatens grid reliability and jobs and defies explanation, business and government leaders from New England said on Monday.State leaders in Connecticut and Rhode Island demanded details from the administration about why it issued a stop-work order to the Revolution Wind project late on Friday. In its letter to project developer Orsted, the Bureau of Ocean Energy Management cited unspecified national security concerns."They say there are national security interests here.
US Halts Revolution Wind Project
The Trump administration on Friday ordered Denmark's Orsted to stop far-advanced construction on an offshore wind project near Rhode Island, in a move that threatens to exacerbate the company's financial troubles.With construction now frozen at 80% completion, Orsted has no immediate path to revenue generation, heightening pressure on the company as it seeks to shore up finances through a $9.4 billion emergency rights issue.The stop-work order, issued by the Bureau of Ocean Energy Management (BOEM), is the administration's latest effort to hinder U.S.
Equinor Might Cancel New York Offshore Wind Project Over Trump Stop-Work Order
The developer of a major U.S. offshore wind project warned that it will cancel the Empire Wind facility off the coast of New York if it cannot reach a resolution over a stop-work order issued by the Trump administration in the coming days.Molly Morris, president of the U.S. renewable energy arm of Norway's Equinor, said the company was spending $50 million a week to keep the project afloat."The situation is now unsustainable," Morris said in an interview.(Reuters)